Food and agriculture · 4,500 headcount, all modules · 2023.
Three entities (~85% of headcount in Indonesia, an international office, and a joint-venture mill), each with different pace and readiness — one was data-ready, one had never used an HR system, one showed low urgency. This was not identified at project start.
Deliver across all three entities despite uneven readiness, while running three other enterprise projects in parallel.
Recognized this was really three projects in one account and restructured it into three separate timelines, each with separate follow-up tracks and different PICs. Escalated the structural risk internally; with no additional support available, took ownership of all three tracks. Kept the ready entity on its own pace so slower ones did not hold it back. Ran a governance cadence per entity for visibility on laggards. Prioritized with an Eisenhower matrix and severity of impact (employees affected).
85% overall go-live within the planned 12 months; full delivery at 18 months, with the delay coming entirely from the two slower entities' readiness. NPS 10. The load was heavy — effectively three accounts — but neither client complained, thanks to the communication built on learning local nuances.
Confirm at kickoff that a client has one accountable PM/owner across all entities. Assess multi-entity readiness before committing the timeline, and size PM capacity to the real number of tracks, not contracts.
Tiga entitas jadi tiga proyek — pastikan kesiapan sebelum menyepakati timeline.