Hospital group · 4,500 headcount · planned 4 months, actual 12 months.

Situation

Positioned as the entry point into a wider healthcare group. In/out-of-scope disputes made the contract difficult from the start and the project charter could not be finalised. Root cause was upstream: pricing was set on assumptions, and the integration scope (SAP and internal hospital systems) was stated in the internal handover as delivered by the client, which the client never confirmed.

Task

Deliver 4,500 headcount on a tight plan while resolving scope gaps that had not been cleared in presales or the POC.

Action

Created a new plan and asked client users for support. Presented trade-offs to the client after internal alignment; agreed the decision and documented it in writing. Asked internal stakeholders for support, since the situation was highly sensitive with added commercial impact.

Result

Timeline extended from 4 to 12 months after rescoping around the integrations. Delivered with ~80 open issues, all traceable back to the rescoping. The client did not submit an NPS score.

Lesson Learned

Involve a PIC with strong product knowledge from the pitch so integration and scope commitments are validated before pricing. Add a handover feedback gate: too many unconfirmed items means the sale goes back to presales before implementation. Every integration owner must be confirmed by the client in writing, not assumed.

Saran saya: wajib ada handover gate — jangan mulai implementasi sebelum semua item terkonfirmasi.